EV charger install permits in Burbank, CA
General California guidance last updated May 22, 2026 · Burbank data verified August 10, 2026
What electrical contractors need to know about pulling a ev charger install permit in Burbank (Los Angeles County).
Short answer
In California, a hardwired Level 2 EV charger (EVSE) install needs an electrical permit because it adds a dedicated circuit and load — generally pulled by a licensed C-10 contractor under the California Electrical Code (Title 24, Part 3, Articles 625 and 220). Most California cities now offer streamlined or instant residential EV-charger permitting under SB 1222 / AB 1236.
Burbank accepts submittal through the Burbank Online Permits (BOP) and has adopted the 2025 California Building Code (with Burbank amendments, BMC Title 9). Fee details and sources are below.
Burbank permit data
Sourced from public City of Burbank documents — every field carries the source URL and verification date.
- Permit portal
- Burbank Online Permits (BOP)
verified Aug 10, 2026 · source · Tier 1 single-family residential permits issue online via BOP; projects requiring plan check submit electronically through ProjectDox (https://burbank-ca-us.avolvecloud.com/Login/Index/BUCA-Prod). A BOP account also pays plan-check and permit fees
- Adopted code edition
2025 California Building Code (with Burbank amendments, BMC Title 9)
verified Aug 10, 2026 · source · In effect as of January 1, 2026 — adopting ordinance No. 25-4,034; applications submitted on or after that date are reviewed under the 2025 California Building Standards Code and local amendments
- Fee schedule
- City of Burbank Citywide Fee Schedule — FY 2026-27 (adopted)
verified Aug 10, 2026 · source · The Citywide Fee Schedule contains the fee amounts of most city-provided services; the Revenue page lists FY 2026-27 as the current schedule
The general picture in California
Adding a hardwired EV charger to a residence or workplace nearly always requires an electrical permit. The install adds a dedicated 240V circuit, typically requires a load calculation against the existing service, and may trigger a panel upgrade if the existing service can't carry the new load. California state law (AB 1236, then SB 1222) requires expedited residential EV-charger permitting — many cities issue same-day or via an online checklist. Plug-in Level 1 chargers using an existing 120V outlet generally don't require a permit; a new dedicated 120V or 240V circuit does.
For deeper background that isn't Burbank-specific, see the statewide ev charger install guide.
Typically needs a permit
EV charger install itself triggers a permit in nearly every California jurisdiction, Burbank included. Burbank-specific variations are confirmed with the issuing department above.
Usually doesn't (general norm)
- Plugging a portable Level 1 charger into an existing, properly-rated receptacle with no new circuit
- Replacing one EVSE with another of the same output on the same existing circuit (verify locally — some cities still require a permit)
Documents & plans generally required
- Electrical permit application — residential EV applications are often a checkbox/streamlined form
- Contractor license and city business registration
- Site plan / location of the charger and the panel
- Load calculation — connected load vs. service capacity (NEC Article 220 + 625.42)
- Single-line diagram showing the new breaker, conductor size, and EVSE
- EVSE manufacturer cut sheet (UL listed; maximum output amps)
- Service-upgrade documentation if the load calc requires it
Common reasons ev charger install applications get bounced
Code-rooted patterns across California — not a Burbank-specific rejection rate.
- Missing or incomplete load calculation showing the new EVSE within service capacity
- Conductor or breaker sizing not at 125% of the EVSE's continuous output
- GFCI protection not specified where required by the current code cycle
- EVSE not listed/labeled by a recognized testing lab, or cut sheet missing
- Outdoor location without a NEMA-rated enclosure or weather-resistant disconnect
- Service capacity exceeded without a panel upgrade or load-management device (EVEMS) shown
The inspection sequence
A typical order — the number of stops and exact sequence vary by jurisdiction and scope.
- 1Rough inspection if conduit/wiring is concealed before cover
- 2Service inspection only if the install includes a panel/service upgrade
- 3Final inspection with the EVSE installed, energized, and tested
Licensing — who can pull it
EV-charger installations in California are generally performed by a C-10 (Electrical) licensed contractor; a B (General Building) contractor may pull within a larger project under CSLB rules. The licensed contractor doing the work typically pulls the permit.
Other verified Burbank notes
Permit counter: Community Services Building, First Floor, 150 N. Third Street, Burbank, CA 91502; Building Permits/Plan Check (818) 238-5220; walk-in Monday–Thursday 8 AM–3:30 PM.
verified Aug 10, 2026 · source
Out-of-town contractors working on a construction project in Burbank pay the city's Contractor's Business Tax per job, collected with issuance of the building permit.
verified Aug 10, 2026 · source
Building inspections are requested one day in advance online through the Burbank Online Permits portal.
verified Aug 10, 2026 · source
Instant, automated solar and battery storage (ESS) permits for single-family residential installations are issued in real time via the city's partnership with Symbium.
verified Aug 10, 2026 · source
Frequently asked questions
Do I need a permit for a Level 2 home EV charger in California?
Generally yes. A hardwired Level 2 EVSE adds a dedicated 240V circuit and is treated as new electrical work — California cities almost universally require a permit. State law (SB 1222) further requires expedited, often online, residential EV-charger permitting.
What about a plug-in Level 2 charger on an existing 240V outlet?
If the 240V receptacle is existing, properly rated for the load, and installed under the original permit, plugging in a portable EVSE usually doesn't trigger a new permit. Installing a new 240V receptacle for that purpose does — that is a new branch circuit.
Will I need a panel upgrade?
It depends on the load calculation. Many homes — especially older ones with 100A service — exceed capacity once an EV charger is added. Load-management devices (EVEMS) can sometimes avoid a panel upgrade by limiting EV draw when the rest of the house is using power.
Can the homeowner pull the permit?
California allows homeowners to perform certain work on their own primary residence, but the work must still meet code and be inspected. getPermit is built for licensed contractors — for owner-pulled permits, contact the city directly.