Electrical panel upgrade permits in Burbank, CA

General California guidance last updated May 22, 2026 · Burbank data verified August 10, 2026

What electrical contractors need to know about pulling a electrical panel upgrade permit in Burbank (Los Angeles County).

Short answer

In California, an electrical service or panel upgrade always needs an electrical permit and an inspection, and almost always requires utility coordination for the temporary disconnect. It is pulled by a licensed C-10 contractor under the California Electrical Code (Title 24, Part 3). Common drivers: EV chargers, heat pumps, solar/battery, ADUs, and replacing legacy/recalled panels (Federal Pacific, Zinsco, Pushmatic).

Burbank accepts submittal through the Burbank Online Permits (BOP) and has adopted the 2025 California Building Code (with Burbank amendments, BMC Title 9). Fee details and sources are below.

Burbank permit data

Sourced from public City of Burbank documents — every field carries the source URL and verification date.

Permit portal
Burbank Online Permits (BOP)

verified Aug 10, 2026 · source · Tier 1 single-family residential permits issue online via BOP; projects requiring plan check submit electronically through ProjectDox (https://burbank-ca-us.avolvecloud.com/Login/Index/BUCA-Prod). A BOP account also pays plan-check and permit fees

Adopted code edition

2025 California Building Code (with Burbank amendments, BMC Title 9)

verified Aug 10, 2026 · source · In effect as of January 1, 2026 — adopting ordinance No. 25-4,034; applications submitted on or after that date are reviewed under the 2025 California Building Standards Code and local amendments

Fee schedule
City of Burbank Citywide Fee Schedule — FY 2026-27 (adopted)

verified Aug 10, 2026 · source · The Citywide Fee Schedule contains the fee amounts of most city-provided services; the Revenue page lists FY 2026-27 as the current schedule

The general picture in California

A panel upgrade changes the building's electrical service — bumping the amperage (typically 100A → 200A, sometimes 225/400A), replacing the panel and meter, and often re-pulling the service lateral or mast. Because the work touches utility infrastructure and the main overcurrent device, it requires an electrical permit, a load calculation, a single-line diagram, and coordination with the utility for power-cut and reconnect. Grounding and bonding must meet the current code cycle (often a new ground-rod system in addition to the UFER), and AFCI/GFCI updates may be required on circuits being touched or extended.

For deeper background that isn't Burbank-specific, see the statewide electrical panel upgrade guide.

Typically needs a permit

Electrical panel upgrade itself triggers a permit in nearly every California jurisdiction, Burbank included. Burbank-specific variations are confirmed with the issuing department above.

Usually doesn't (general norm)

  • Replacing a single breaker for one of the same type and rating
  • Tightening lugs or replacing a feeder bus cover (maintenance, not modification)
  • Re-labeling the panel directory

Documents & plans generally required

Common reasons electrical panel upgrade applications get bounced

Code-rooted patterns across California — not a Burbank-specific rejection rate.

The inspection sequence

A typical order — the number of stops and exact sequence vary by jurisdiction and scope.

  1. 1Rough/service inspection before energization, with the panel set and grounding visible
  2. 2Utility coordination for temporary disconnect, meter pull, and reconnect
  3. 3Final inspection with the panel labeled, all circuits identified, and the service energized

Licensing — who can pull it

Panel and service upgrades in California are performed by a C-10 (Electrical) licensed contractor; a B (General Building) contractor may pull within a larger project under CSLB rules. The licensed contractor pulling the permit typically also coordinates the utility cut and reconnect.

Other verified Burbank notes

Frequently asked questions

When does California require a panel upgrade?

When the load calculation shows the existing service can't carry the new connected load — most often triggered by EV chargers, heat pumps, solar/battery, ADUs, or replacing a recalled panel brand (Federal Pacific, Zinsco). The upgrade is permitted as a single project even when it bundles multiple drivers.

Do I need to coordinate with the utility?

Yes — service upgrades require utility coordination for the temporary disconnect, meter pull, and reconnect. PG&E, SCE, LADWP, and SDG&E each have their own application and lead time; the contractor typically handles this in parallel with the city permit.

Can I keep the same panel location?

Generally yes, if the location still meets NEC 110.26 working clearances and the meter remains accessible to the utility. Moving the panel can simplify the install or be required when the existing location is non-compliant.

Does the panel upgrade trigger AFCI/GFCI updates on existing circuits?

Generally only the circuits being touched, extended, or replaced have to meet the current code cycle's AFCI/GFCI rules — existing circuits left in place are usually grandfathered. Some jurisdictions are stricter on this; confirm with the city.