Building permits in Mesa, AZ
Early Arizona guides. getPermit is California-first — these pages share what we've verified in Arizona so far, and they don't mean getPermit covers Arizona yet. Join the waitlist with your city to tell us where to go deeper.
Mesa (Maricopa County) adopts its own building code editions — Arizona has no statewide building code — and runs its own permit intake, forms, fees, and inspections. Here's what we've verified and where to confirm the specifics.
Mesa's Development Services runs permitting electronically through DIMES under the 2024 International Codes and the 2023 NEC, in effect for applications submitted on or after January 8, 2026. Mesa's city code exempts several like-for-like swaps — AC, heat pump, and furnace replacements of equal or less amperage, water heaters of equal or lesser rating, and roof coverings of equal or greater classification — while EV chargers, gas piping, batteries, and meter panel upgrades need permits. Plan reviews return comments or approval within 10 working days, counting Monday through Thursday.
Verified local data — Mesa
Every fact below is sourced from a public City of Mesa document or portal page. Each carries the source URL and the date we last verified it. Full dataset last re-verified .
- Permit portal
- DIMES (Accela Citizen Access)
verified Sep 13, 2026 · source · Handles applications, plan uploads, fees, and inspections. Mesa Electric solar interconnection applications use a separate form linked from the City's Solar Program page
- Submission methods
Online
verified Sep 13, 2026 · source · The residential construction guide states that all permit applications, plan review, documents, and approvals are electronic
- Adopted code edition
2024 IBC, IRC, IMC, IPC, IFGC, IECC, IEBC, ISPSC, and IFC, and the 2023 NEC — in effect for permit applications submitted on or after January 8, 2026
verified Sep 13, 2026 · source · Ordinances 5980 (IBC) and 5981 (IRC) per the December 1, 2025 City Council minutes; Ordinance 5982 (NEC) adopted December 8, 2025
- Fee schedule
- Schedule of Fees and Charges — Development Services (updated for July 2026)
verified Sep 13, 2026 · source · Page footers read "Updated for July 2026"; the schedule states no separate 2026 effective date
Other local notes
Replacing electric air-conditioning units, air handlers, heat pumps, or furnaces of equal or less amperage is exempt from a permit, and so is replacing a gas furnace of equal or less Btu/cfh, provided the serving gas utility is notified before it is energized.
verified Sep 13, 2026 · source · Mesa City Code §4-1-4(B). The City's residential FAQ adds: "If you're changing the electrical connections, you will need a construction permit" — https://www.mesaaz.gov/Business-Development/Development-Services/Building-Permit-Plan-Review/Residential-Construction/Residential-Construction-FAQ
Like-for-like water heater replacements of equal or lesser rating need no permit; replacing a gas storage water heater with a tankless or on-demand gas unit does.
verified Sep 13, 2026 · source
An equal replacement of the exterior water supply line to a building, or of the exterior sanitary drain line from it, is exempt from a permit when the line isn't in a public utility easement or City right-of-way.
verified Sep 13, 2026 · source · Mesa City Code §4-1-4(B)5(l) and (m)
A new roof covering needs no permit when its classification is equal to or greater than the existing roof covering's.
verified Sep 13, 2026 · source · Mesa City Code §4-1-4(B)1(n)
Photovoltaic systems that are listed and labeled by a nationally recognized testing agency, under 10,000 square feet, and installed by an Arizona-licensed contractor are exempt from a permit.
verified Sep 13, 2026 · source · Mesa City Code §4-1-4(B)2(r)
A solar system that includes a battery or a meter panel upgrade needs a Development Services permit, and Mesa Electric customers must have their interconnection application accepted before installation.
verified Sep 13, 2026 · source
Residential EV charger applications need a site plan, equipment spec sheets, the panel's location, size, and capacity, circuit and wire sizing, and a complete panel schedule with load calculations for all appliances.
verified Sep 13, 2026 · source
Residential gas piping plans show each appliance's BTU load, a piping diagram with size, length, and material, and underground routing and burial depth; gas lines may not be located in a public utility easement.
verified Sep 13, 2026 · source
Contractors must not disconnect utility wires or meters; disconnects and reconnects are scheduled with the serving utility.
verified Sep 13, 2026 · source
Permit applicants provide their ROC license number on the City's Contractor Licensure Verification form.
verified Sep 13, 2026 · source
Plan reviews return written comments or approval within 10 working days, counting Monday through Thursday and excluding holidays; expedited review takes 5 working days.
verified Sep 13, 2026 · source
Inspections are scheduled online, by phone at 480-644-2428, or by text, using three-digit inspection codes.
verified Sep 13, 2026 · source
Official building department
City of Mesa Development ServicesVerified Mesa specifics are shown above. For project-specific fees, timelines, and counter staff, this department is the authority.
Common jobs in Mesa
The general Arizona guide for each job. Mesa's verified local data, including job-by-job permit notes, is shown above.