The three Title 24 Energy Code forms on a California changeout, compared in one table: the CF1R (Certificate of Compliance), the CF2R the installer signs and the CF3R the ECC-Rater (still called the HERS rater) signs. When an AC, furnace, heat pump, duct or water heater job needs rater verification under 2025 Energy Code §150.2(b), the order of the paperwork, and a one-screen checklist.

Updated 14 min readTitle 24HERS / ECC-RaterChangeouts
A duct leakage test in a carpeted hallway: a black round test fan sealed with a gray fabric shroud over a wall return-air grille, red and clear pressure tubes running to a yellow handheld gauge on a hard instrument case, and a technician in a hard hat and hi-vis vest writing on a clipboard by a window at the end of the hall
On this page
  1. CF1R, CF2R and CF3R compared
  2. ECC-Rater or HERS rater: the same job
  3. When a changeout needs ECC-Rater (HERS) verification
  4. The order of the paperwork
  5. What changed with the 2025 code
  6. Changeout checklist

On a California HVAC or water heater changeout, the Energy Code paperwork is three certificates: the CF1R, the CF2R and the CF3R, often called the Title 24 forms. Every requirement links to the 2025 Energy Code section or Energy Commission page it comes from, read on November 14, 2026. This guide covers single-family homes and is not legal advice.

CF1R, CF2R and CF3R compared

The CF1R (Certificate of Compliance) says what the job must meet and goes to the city with the application. The CF2R (Certificate of Installation) is the installing contractor's signed statement that the work meets it. The CF3R (Certificate of Verification) is the ECC-Rater's test record. The city won't approve the job without the ones it needs.

FormName in the codeWho fills and signs itWhen it's dueSource
CF1RCertificate of ComplianceThe person eligible under the license law (Bus. & Prof. Code, Division 3) to take responsibility for the design, plus the documentation author who prepared it. For an alteration, the owner or the owner's agent; an ECC-Rater may prepare it with the owner's authorizationRegistered, then submitted with the permit application. On an alteration needing verification where the city requires no plans, it may be approved after the permit issues but before final inspectionPart 1 §10-103(a)1, (a)2A; RA2.8
CF2RCertificate of InstallationThe person in charge of the installation who is eligible under the license law to take responsibility for it (the installing contractor), or an Authorized Representative under a written agreement, plus the documentation author who prepared it (can be the same person)After the install and the installer's own diagnostic tests; registered when the job needs verification, and posted or made available at the site for inspectionsPart 1 §10-103(a)3; RA2.3.2
CF3RCertificate of VerificationThe certified ECC-Rater who did the field verification and diagnostic testing, plus the documentation author, with electronic signatures onlyAfter the CF1R and CF2R are registered and the rater has tested; registered before the city approves the job, except that under a Third Party Quality Control Program the city may approve on the CF2R first, on conditionsPart 1 §10-103(a)5; RA2.3.2, RA2.8
  • The forms are statewide. Each certificate must follow "a format and informational order and content approved by the Energy Commission" (Part 1 §10-103(a)1A, (a)3B, (a)5A). The city sets the permit application, fees and inspections, not the CF forms. The one exception: for alterations that need no field verification, it may waive the CF1R and CF2R or make simplified ones (Part 1 §10-103(a)1C, (a)3D).
  • Registered means filed in an ECC-Provider's data registry. When a job needs field verification, all three certificates are registered there, and each shows its registration number (RA2.3.1.2; Part 1 §10-103(a)1A). The Energy Commission doesn't register documents itself (ECC Program page). On November 14, 2026, its ECC-Provider page listed one approved provider for the 2025 code, CHEERS, approved November 12, 2025.
  • The form numbers for changeouts. The Energy Commission's single-family forms page lists CF1R-ALT-02-E (prescriptive alterations to space conditioning systems, registered) and, for alterations that need no field verification, CF1R-ALT-05-E and CF2R-ALT-05-E (not registered). The installer's mechanical CF2Rs include CF2R-MCH-01b-E (ducts and fans, prescriptive alterations), CF2R-MCH-20-H (duct leakage), CF2R-MCH-22-H (fan efficacy), CF2R-MCH-23-H (airflow) and CF2R-MCH-25-H (refrigerant charge); the rater's CF3R-MCH forms carry the same numbers.
  • Copies for the owner. At final inspection the city must have the contractor leave copies of the CF1R, CF2R and CF3R in the building for the owner (Part 1 §10-103(b)1A).

ECC-Rater or HERS rater: the same job

The 2025 Energy Code, in effect since January 1, 2026, calls the third-party tester an ECC-Rater; contractors, cities and rater companies still say HERS rater. It is the same job: field verification and diagnostic testing of the measures the CF1R lists. The program was renamed from the HERS Program to the Energy Code Compliance (ECC) Program, and a few procedures changed with it (see "What changed with the 2025 code").

  • The definition. An ECC-Rater "is a person trained, tested, and certified by an ECC-Provider to perform field verification and diagnostic testing for the ECC program" (Part 1 §10-102).
  • Why the name changed. The field-verification part of the Title 20 HERS regulations moved into Title 24 with the 2025 code. The Energy Commission says "all HERS raters will be recognized as ECC-Raters," rater businesses may keep "HERS" in their names, and the 2025 forms replace "HERS" with "ECC" or "FV&DT"; the CF1R's "HERS FEATURE SUMMARY" becomes the "ECC FEATURE SUMMARY" (ECC Program page).
  • Older permits keep the older rules. A project permitted under the 2022 code is verified to the 2022 code, and its forms keep the HERS terms (ECC Program page).
  • The rater is independent of you. ECC-Raters and rater companies "shall not have any financial interest in the builder, designer, or subcontractor" who signs the CF1R or CF2R, where a financial interest includes an employer-employee relationship; they may not do construction work on a site they will verify, or test for close relatives (Part 1 §10-103.3(b)1A). The exception is a rater company that also offers design, permitting or signing services on the same project: it files a Declaration of ECC-Rater Company Separation of Services showing those staff have no management, hiring, payment or other authority over its rater (§10-103.3(f)2Diii).
  • Cost. The code sets no rater fee. The rater company sets its price, and the city sets the permit fee.

When a changeout needs ECC-Rater (HERS) verification

On a ducted AC, heat pump or furnace changeout, usually. Replacing the condenser, coil or air handler triggers duct sealing with rater-verified testing in every climate zone. When refrigerant parts are replaced, air conditioners in Climate Zones 2 and 8 through 15 and heat pumps everywhere add refrigerant charge and airflow. A water heater replacement under the prescriptive rules needs none.

Each trigger below is stated as the 2025 Energy Code states it, for the prescriptive approach most changeouts use. Under the performance approach, any measure the CF1R takes a verified credit for also has to be verified by an ECC-Rater (§150.2(b)2B). Sections 150.2(b)1C through 1H are in Subchapter 9; §150.0(m)13 is in Subchapter 7.

The jobThe trigger in the codeWhat gets verifiedExceptionsSection
Replacing the air handler or furnace, the outdoor condensing unit of a split AC or heat pump, or a cooling or heating coil"In all climate zones," installing or replacing space-conditioning equipmentThe connected duct system is sealed: leakage at or under 10% of air handler airflow, or 7% to outside, or, if neither is possible, every accessible leak sealed and checked by visual inspection and a smoke test by an ECC-RaterDucts documented as previously sealed and confirmed by field verification and diagnostic testing; duct systems "with less than 40 linear feet"; ducts constructed, insulated or sealed with asbestos§150.2(b)1E
Installing more than 25 feet of new or replacement duct"In all climate zones, when more than 25 feet of new or replacement space-conditioning system ducts are installed"New ducts in unconditioned space insulated to R-6 (Climate Zones 3, 5 to 7) or R-8 (all others). An entirely new or complete replacement duct system (at least 75% new duct material; reused parts must be accessible and sealable): 5% leakage, plus the air filter rules (§150.0(m)12) and, on a system that supplies cooling, the airflow and fan watt draw limits of §150.0(m)13 (see the complete-system row). An extension: 10%, or 7% to outside; the smoke test only if neither is possibleExtended ducts constructed, insulated or sealed with asbestos§150.2(b)1D
Altered ducts, air handler, coil or plenum in a garageAny length of ductLeakage at or under 6%, or all accessible garage leaks sealed and smoke-tested by an ECC-RaterNone listed§150.2(b)1Diic
Replacing a refrigerant part (compressor, condensing or evaporator coil, metering device, refrigerant piping) on an air-cooled AC in Climate Zones 2 and 8 to 15, or on an air-source heat pump in any zone, mini-splits includedThe system "is altered by the installation or replacement of refrigerant-containing system components"Airflow of at least 300 cfm per ton (250 for small-duct high-velocity) on systems the airflow procedure can test; a system that can't reach it uses an alternative procedure and a §110.12 thermostat. Refrigerant charge on all of them: the installer charges to the manufacturer's specs and the rater verifies itA new factory-charged packaged unit needs no field charge check; the installer certifies it on the CF2R, and a ducted unit still gets the airflow test if the procedure can test it. Below 55°F outdoors, a weigh-in path that then needs a §110.12 thermostat§150.2(b)1F
A complete replacement system: all the equipment plus an entirely new or replacement duct system"Entirely new or complete replacement space-conditioning systems"The new duct system's 5% leakage test and the charge check above. On a system with ducts that supply cooling, also at least 350 cfm per ton in every control mode and fan watt draw (fan efficacy) of 0.45 W/cfm or less for a gas furnace air handler or 0.58 W/cfm for others (a single-zone system's gas furnace made before July 3, 2019 may use 0.58); small-duct high-velocity systems, 250 cfm per ton and 0.62 W/cfmDucted systems without zoning dampers may instead meet the return duct and filter sizing tables (150.0-B, 150.0-C), also field-verified§150.2(b)1C; §150.0(m)13
Replacing a water heater, heat pump water heaters included"Altered or replacement service water-heating systems or components"No ECC-Rater verification. The rules: pipe insulation, demand recirculation with manual control where there is a recirculation loop, and an allowed water heater typeNot applicable§150.2(b)1H
  • Thermostats come with the refrigerant work. When §150.2(b)1F applies, "all thermostats associated with the system shall be replaced with setback thermostats" meeting §110.2(c), in any climate zone. The code doesn't call for field verification of it.
  • The charge check has two paths. Either the installer and the rater both run the standard charge verification procedure, or the installer weighs in the charge and the ECC-Rater verifies it. Systems the standard procedure can't test, which can include mini-splits, use the weigh-in with the rater verifying it under RA3.2.3.2 (§150.2(b)1Fii–iii). The Energy Commission's compliance manual says that verification "can be accomplished only by simultaneous observation of the installer's weigh-in," so the rater has to be there for it (2025 Single-Family Residential Compliance Manual, p. 4-73).
  • New mini-splits count. The same manual reads §150.2(b)1F to apply when a refrigerant-containing component is "replaced or installed in an existing house," and says replacing the outdoor unit alone triggers duct sealing (pp. 9-39 and 9-40).
  • Heat pump water heaters. §150.2(b)1H allows a gas or propane water heater; a single heat pump water heater whose tank is not outdoors, sits on an incompressible, rigid insulated surface of at least R-10, and has a communication interface meeting §110.12(a) or an ANSI/CTA-2045-B port; a single heat pump water heater meeting NEEA Advanced Water Heater Specification Tier 3 or higher; if the old one was electric resistance, a consumer electric water heater; or a system the Energy Commission's Executive Director finds uses no more energy than one of those.
  • Water heater paperwork can be lighter. For alterations "for which field verification is not required, including but not limited to water heater and window replacements," the city may require no Certificate of Compliance or Installation, or use simplified ones (Part 1 §10-103(a)1C, (a)3D). §150.2(b)1H itself calls for no rater; the hot water verification measures in Table RA2-6 apply only where a CF1R claims them (Table RA2-6).
  • New heating equipment can't be electric resistance. An altered or replacement space-heating system "shall not use electric resistance as the primary heat source," with exceptions when the old system was electric resistance (§150.2(b)1G).

The order of the paperwork

Register the CF1R, book the rater before you install, finish and test the work, register your CF2R, let the rater test and register the CF3R, then call for final. The city won't approve the alteration until it has the CF2R and CF3R, except under a Third Party Quality Control Program.

  1. CF1R. The owner or the owner's agent registers it in an ECC-Provider's data registry and submits it to the city. With the application if the city wants plans; otherwise it can be approved after the permit issues, as long as that happens before final inspection (RA2.8; Part 1 §10-103(a)2A). The Energy Commission calls this the exception for "urgent alterations (e.g., HVAC changeouts)" (ECC Program page).
  2. Book the rater before the install. The code puts it on the builder to arrange the rater "prior to installation of the measures," so the test doesn't delay final approval (RA2.3.2(b)). On a system the standard charge procedure can't test, such as some mini-splits, book the rater for the day you weigh in the charge: the rater verifies it only "by simultaneous observation of the installer's weigh-in" (compliance manual, p. 4-73).
  3. Install, test, register the CF2R. Run your own diagnostic tests; if they pass, register the CF2R and post a copy at the site (RA2.3.2(b)).
  4. The rater tests and registers the CF3R. The rater first confirms the CF1R and CF2R are registered (RA2.3.2(c)). If a test fails, "the contractor is required to fix the feature or system until it passes" (ECC Program page). An alteration is verified on its own: it can't be put in a sample group (RA2.8).
  5. Final inspection. "The enforcement agency shall not approve the alteration until the enforcement agency has received a completed Certificate of Installation" and "a completed Certificate of Verification" (RA2.8; Part 1 §10-103(d)2). For a single-family home, final inspection isn't complete until the city has verified that. The exception: under a Third Party Quality Control Program, the city may approve on the CF2R before the CF3R is registered, where the program's data checking shows the unit complies and on the condition that the CF3R follows (RA2.8).
  6. Leave the copies. CF1R, CF2R and CF3R stay in the home for the owner (Part 1 §10-103(b)1A).

What changed with the 2025 code

The duct sealing triggers read the same as in the 2022 code: "in all climate zones," and more than 25 feet of duct. What changed on January 1, 2026 is the program around them: its name, the forms, the refrigerant charge methods, and the end of group sampling for alterations.

  • January 1, 2026. The ECC Program took effect with the 2025 Energy Code; HERS terms were replaced on 2025 forms and software. Group sampling for alteration projects was removed, the weigh-in charge methods (RA3.2.3) were revised, and a fault indicator display alone may no longer be used to show the refrigerant charge is right (ECC Program page).
  • The duct numbers. §150.2(b)1D says "more than 25 feet" and §150.2(b)1E says "in all climate zones" in the 2025 code and in the 2022 code. The 40 feet in the 2025 code is the §150.2(b)1E exception for duct systems under 40 linear feet, a different rule.

Changeout checklist

The checklist follows the prescriptive path most changeouts use. Run only the tests your CF1R lists. Each line cites its section; the sections above link the sources and carry the exceptions.

Before you file

  • Name the scope: equipment only, refrigerant parts, more than 25 feet of duct, a complete system, or a water heater (§150.2(b)1C–H).
  • Find the climate zone. Refrigerant charge on an air conditioner is checked only in Zones 2 and 8 to 15; on a heat pump, in every zone (§150.2(b)1F).
  • Register the CF1R (CF1R-ALT-02-E for an HVAC changeout that needs verification) in an ECC-Provider's registry (Part 1 §10-103(a)1; RA2.8).
  • Ask the city whether it wants the CF1R with the application or before final (Part 1 §10-103(a)2A).

Before you install

  • Book the ECC-Rater (HERS rater): a company with no financial tie to you (RA2.3.2(b); Part 1 §10-103.3(b)1A).
  • If the rater will verify your weigh-in, book them for the day you charge the system (§150.2(b)1Fiii; RA3.2.3.2).
  • Plan setback thermostats if refrigerant parts are being replaced (§150.2(b)1Fi).

After you install

  • Run your own diagnostic tests for the measures the CF1R lists (RA2.3.2(b)).
  • Register your CF2Rs and post copies at the site (Part 1 §10-103(a)3).
  • Let the rater test and register the CF3Rs; fix and retest anything that fails (Part 1 §10-103(a)5).

At final

  • Have the CF2R and CF3R available for the inspector; the city won't approve the job without them unless a Third Party Quality Control Program is used (RA2.8).
  • Leave copies of the CF1R, CF2R and CF3R in the home for the owner (Part 1 §10-103(b)1A).

Water heater only: no rater under the prescriptive rules (§150.2(b)1H); ask the city which Energy Code form, if any, it wants (Part 1 §10-103(a)1C).

For the city inspections around these steps, see California building inspections for contractors; for the job-by-job permit scope, the guides to the AC changeout, furnace replacement, duct replacement, mini-split installation and water heater replacement.

FAQs

What is a CF1R?

The CF1R is the Certificate of Compliance: the Energy Code form that lists the energy features the job must meet and, where they apply, the measures an ECC-Rater (HERS rater) has to verify. For an HVAC changeout that needs verification it is the registered CF1R-ALT-02-E, submitted to the building department with the permit application, or, where the city asks for no plans, approved before final inspection (Title 24, Part 1, §10-103(a)1 and (a)2A).

Who signs the CF2R?

The person in charge of the installation who is eligible under the license law (Business and Professions Code, Division 3) to take responsibility for it, which on a changeout is the installing contractor, or an Authorized Representative under a written agreement kept in the ECC-Provider's data registry. The documentation author who prepared it signs too; one person can do both. When the job needs rater verification, the CF2R is registered in that registry and made available at the site for inspection (Title 24, Part 1, §10-103(a)3).

Is a HERS rater the same as an ECC-Rater?

Yes. The 2025 Energy Code, in effect since January 1, 2026, moved field verification from the Title 20 HERS program into Title 24 and named it the Energy Code Compliance (ECC) Program. The Energy Commission recognizes every HERS rater as an ECC-Rater, and rater companies may keep HERS in their names. Contractors and cities still say HERS; the 2025 forms say ECC.

Does a water heater replacement need HERS testing in California?

Not under the prescriptive rules. 2025 Energy Code §150.2(b)1H sets pipe insulation, recirculation controls and the allowed water heater types, including the heat pump water heater installation rules, and lists no ECC-Rater verification. For alterations that need no field verification, including water heater replacements, the city may skip the Energy Code forms or use simplified ones (Title 24, Part 1, §10-103(a)1C).

Does a like-for-like AC changeout need HERS testing?

Usually. Replacing the condenser, coil or air handler triggers duct sealing with field verification in every climate zone (§150.2(b)1E), unless the ducts are documented as already sealed and field-tested, total under 40 linear feet, or were made, insulated or sealed with asbestos. When refrigerant parts such as the condenser or coil are replaced, air conditioners in Climate Zones 2 and 8 through 15 and heat pumps everywhere also get refrigerant charge verification, plus airflow on ducted systems the test can check; a new factory-charged packaged unit skips the field charge check (§150.2(b)1F). Replacing only the furnace or air handler doesn't trigger the charge check.

Can someone from my company do the HERS test?

No, as a rule. ECC-Raters and rater companies may have no financial interest in the builder or subcontractor who signs the CF1R or CF2R, which includes being their employee, and may not do construction work on a site they verify or test for close relatives (Title 24, Part 1, §10-103.3(b)1A). The one exception is a rater company that also does design, permitting or signing work on the project and files a declaration that those people have no authority over its rater (§10-103.3(f)2Diii).

Pulling permits in California?

Join the waitlist. We prioritize the cities and trades our early users work in.