Guide · New laws
California permit laws taking effect 2027 to 2028
Five California laws signed in 2026 take effect January 1, 2027, with new duties phasing in through July 1, 2028: a heat pump permit fee cap and real-time online permits (SB 222, Gov. Code §51297.50 et seq.), remote inspections (AB 1738), a two-review plan check limit (AB 1621), EV charger approvals (SB 1283), and ADU impact fees (SB 1117). Dates, exceptions, and code sections.

On this page
Five laws signed in September 2026 change how California cities permit and inspect work that trade contractors do every week: heat pumps, reroofs, small solar, EV chargers, ADUs, and plan check on housing. None carries an urgency clause, so all five take effect January 1, 2027 (Cal. Const., art. IV, §8(c)(1)), and the new duties phase in through July 1, 2028. Every row below was read from the chaptered bill text.
The five laws at a glance
SB 222 and AB 1738 change heat pump permits and inspections. AB 1621 limits plan check rounds on housing, SB 1283 widens EV charger approvals, and SB 1117 trims ADU impact fees. All five are chapters of the Statutes of 2026.
| Law and code section | What changes | Operative | Exceptions | Our guide |
|---|---|---|---|---|
| SB 222, Ch. 738. Gov. Code §§51297.50–51297.59; Civ. Code §4737 | Heat pump permits in existing homes: permit fee capped at $150 (water heater) or $200 (HVAC), requirements and fees posted online, asynchronous inspections, real-time online permits for swapouts | January 1, 2027: fee cap, posted fees, limits on local standards. July 1, 2027: asynchronous inspections. July 1, 2028: real-time online permits | Not new construction. Cities under 5,000 and counties under 150,000, with their cities, are exempt from the fee cap, the posting duty, and online permits. A city may adopt a higher fee with a cost finding | Building inspections |
| AB 1738, Ch. 271. Health and Safety Code §17970.9 | Remote inspections on request, by video call or recorded photos and video, for heat pumps, residential reroofs, PV up to 15 kW AC, energy storage, and smoke and CO detectors in one- and two-family homes, at no greater cost or delay than in person | By January 1, 2028. By July 1, 2028 in cities of 50,000 or fewer | Cities under 5,000 and counties under 150,000, with their cities, are exempt. A new or upgraded main electrical service need not be inspected remotely. The inspector may require an in-person inspection | Building inspections |
| AB 1621, Ch. 780. Gov. Code §65913.3 | Housing development projects: no more than two plan check reviews for a building permit, no changes to approved plans at inspection without written findings, appeals decided in 30 or 45 business days | January 1, 2027 | Housing development projects only. After two reviews the city may deny. Grading and offsite improvement permits are not limited | How long a permit takes |
| SB 1283, Ch. 347. Gov. Code §§65850.7, 65850.71 | EV charger permits: streamlined approval also covers a canopy and on-site battery storage sized for charging, written notice within 30 days of a deemed approval, a default application list where a city has no updated checklist | January 1, 2027. Cities amend ordinances and checklists by December 31, 2027 | The city can still require the plans and documents needed to verify health and safety, inspect the work, and require a use permit on a finding of specific, adverse impact | EV charger install |
| SB 1117, Ch. 809. Gov. Code §66311.5 | ADU impact fees: on an ADU over 750 square feet, the fee is charged only on the area above 750 square feet | January 1, 2027 | Up to two ADUs on a lot. With more than two, the fee stays proportional on the whole unit. Connection fees and capacity charges are not impact fees | ADU impact fees |
Heat pump permits: SB 222
SB 222 caps a city's permit fee for a heat pump in an existing home at $150 for a water heater and $200 for HVAC, makes cities post their requirements and fees online, and adds inspections that don't need you and the inspector on site together. By July 1, 2028, permits for qualifying swapouts must issue online in real time (Gov. Code §§51297.52, 51297.55–51297.57).
SB 222 (Chapter 738, Statutes of 2026) was approved by the Governor on September 28, 2026. It adds Chapter 7.5 to the Government Code (§§51297.50–51297.59) and §4737 to the Civil Code. The chapter covers "a single heat pump water heater or heat pump HVAC system that serves one residential dwelling unit" (§51297.51(c)), applies in charter cities too (§51297.50(a)), and does not apply to new residential construction (§51297.59). A section with no date of its own applies from January 1, 2027, when the act takes effect (Cal. Const., art. IV, §8(c)(1)).
Fees
- The cap. A city or county may not charge a permit fee that "exceeds the estimated reasonable cost of providing the service for which the fee is charged" or, unless it adopts a higher fee as described next, $150 for a residential heat pump water heater or $200 for a residential heat pump HVAC system (§51297.57(a)(1)).
- How a city can charge more. Only with a written finding and an adopted resolution or ordinance that gives substantial evidence of its reasonable cost. That fee must be a fixed amount per appliance type and listed publicly (§51297.57(b)), and the city may not add charges above the listed fee (§51297.57(c)).
- What the cap leaves out. Technology fees that third-party vendors charge for the software a city uses to check compliance and issue permits (§51297.57(a)(3)).
- Who is exempt. A city with fewer than 5,000 people, and a county with fewer than 150,000 along with each city in it (§51297.57(a)(2)).
The cap is a ceiling in state law, not what any city charges. For a city's actual fee, read its posted schedule; the city guides link each one.
The permit
- One permit per installation. In the statute's words: "On or before January 1, 2028, a city, county, or city and county may require up to one nondiscretionary permit per installation" of a heat pump, approved administratively (§51297.53(a)). Separate permits are still allowed for a panel replacement or structural work (§51297.53(b)), and a building official can require more than one on written findings of a specific, adverse impact on public health or safety that can't feasibly be mitigated (§51297.53(c)).
- No site plan for a swapout. Where a city asks for a site plan, it may require only information relevant to the installation or to setbacks, and none at all for a swapout. Local setback standards for the equipment can't exceed 3 feet in side and back yards or 10 feet in front yards (§51297.54(a)(1)).
- Posted rules and fees. Cities must publish on their website the local standards they apply, the documents the permit needs, and every fee with its amount, and must accept electronic applications and electronic signatures (§51297.56(a)–(b)). The same small cities and counties are exempt (§51297.56(c)).
- Window units. No permit or inspection for a plug-in window air conditioner or window heat pump that is rated 120 volts or less, is self-contained, and needs no dedicated circuit, panel upgrade, drainage, or structural work (§51297.54(b)).
- Real-time online permits by July 1, 2028. Cities must run an online, automated process that issues the permit in real time to a licensed contractor when the job is a swapout and needs no new electrical panel or structural work. For heat pump HVAC, the contractor certifies under penalty of perjury that a load calculation was done to size the equipment (ACCA Manual J, the SMACNA residential standards, or the California Mechanical Code) and provides it on request (§51297.55(a)). If the city requires a CF1R (the Energy Code compliance form) with the application, it can't ask again for what the CF1R already shows, other than the applicant's name and the project address (§51297.55(b)(2)). Small cities and counties are exempt (§51297.55(d)).
What counts as a swapout
A swapout is an installation where the new heat pump water heater, or the new air handler and outdoor coil, goes "in the same location on a property" as the water heater, or the air handler and condenser, it replaces (§51297.51(d)(1)). It is not a swapout if the job modifies, replaces, or installs more than 25 linear feet of ductwork, or if it changes a package unit to a split system or the reverse (§51297.51(d)(2)).
Inspections
From July 1, 2027, cities and counties must "adopt and offer asynchronous inspections" for these installations: inspections that don't require the licensed contractor and the building inspector to be present at the same time (§51297.52(a)). This section has no population exemption. The inspector can phone or video-call you during the inspection, and can require a joint visit when a test, a fix, or access needs you there (§51297.52(b)–(d)). A city may offer a remote inspection instead (§51297.52(f)). The inspections guide covers how that works.
Condos and HOAs
Civil Code §4737 voids HOA rules that prevent replacing a gas appliance with a code-compliant electric one (§4737(a)). An association also can't prohibit or restrict a heat pump in a member's separate interest (the separately owned unit or lot; Civ. Code §4185), charge a fee for the installation, or require a particular contractor or product, unless the installation would violate the law or a required permit isn't granted (§4737(b)).
What a heat pump permit takes today is in the mini-split guide and in each city's HVAC guide, linked from the city guides.
Remote inspections: AB 1738
By January 1, 2028, cities and counties must let a homeowner, or a contractor with the homeowner's written consent, request a remote inspection for heat pump, reroof, small solar, battery storage, and smoke and CO detector permits in one- and two-family homes. Cities of 50,000 or fewer have until July 1, 2028, and the smallest are exempt (Health and Safety Code §17970.9(a)–(b)).
AB 1738 (Chapter 271, Statutes of 2026) was approved by the Governor on September 18, 2026 and adds §17970.9 to the Health and Safety Code.
- Which work. Residential heat pump water heaters and heat pump HVAC systems, with the electrical work that supports them; residential reroofs; photovoltaic systems of 15 kilowatts AC or less; energy storage systems; smoke and carbon monoxide detectors (§17970.9(a)(1)).
- How. Offsite, by videoconference or by recorded photos and video, at the inspector's discretion (§17970.9(a)(2)).
- Same cost, same speed. "A local agency shall offer a remote inspection at no greater cost and with no greater delay than in-person inspection" (§17970.9(f)).
- Limits. A new or upgraded main electrical service need not be inspected remotely, and heat pump HVAC is covered at the inspector's discretion (§17970.9(a)(1)(A)–(B)). An inspector who can't verify compliance remotely may end the remote inspection and require one in person (§17970.9(e)(2)).
- Who is exempt. A city with fewer than 5,000 people, and a county with fewer than 150,000 along with each city in it (§17970.9(b)(1)).
- Misrepresentation. Willfully misrepresenting the work can get a homeowner or contractor banned from remote inspections for up to 6 months, and up to 12 months after a first offense (§17970.9(h)).
The inspections guide goes through the section subdivision by subdivision.
Asynchronous or remote: the difference
The two laws overlap on heat pumps and are easy to mix up.
| Asynchronous inspection (SB 222) | Remote inspection (AB 1738) | |
|---|---|---|
| What it is | An inspection that doesn't require the contractor and the inspector to be present at the same time (Gov. Code §51297.52(a)) | An offsite inspection by videoconference or recorded photos and video (Health and Safety Code §17970.9(a)(2)) |
| Work covered | Heat pump water heaters and heat pump HVAC serving one dwelling unit, not new construction (§51297.51(c), §51297.59) | Heat pumps, residential reroofs, PV of 15 kW AC or less, energy storage, smoke and CO detectors, in single- or two-family dwelling units (§17970.9(a)(1)) |
| Starts | July 1, 2027 (§51297.52(a)) | By January 1, 2028; by July 1, 2028 in cities of 50,000 or fewer (§17970.9(b)(2)–(3), (j)(2)) |
| Population exemption | None in the section | Cities under 5,000; counties under 150,000 and their cities (§17970.9(b)(1)) |
| Who starts it | The city must adopt and offer it (§51297.52(a)) | The homeowner, or a contractor with the homeowner's written consent (§17970.9(a)(1)) |
| The city's alternative | A remote inspection instead (§51297.52(f)) | An in-person inspection when compliance can't be verified remotely (§17970.9(e)(2)) |
Plan check on housing: AB 1621
From January 1, 2027, a city may not require or request more than two plan check reviews for a building permit on a housing development project. It also can't use an inspection to demand changes to approved plans without written findings, and it must decide an appeal within 30 or 45 business days (Gov. Code §65913.3(c)–(e)).
AB 1621 (Chapter 780, Statutes of 2026) was approved by the Governor on September 29, 2026 and amends Gov. Code §§65589.5 and 65913.3.
- Two reviews. The city "shall not require or request more than two plan check and specification reviews in connection with an application for a building permit" (§65913.3(c)(1)(C)(i), (c)(2)(C)(i)).
- Exceptions. After two reviews the city may deny an application that still doesn't comply, and you may ask for more submittals (clauses (ii) and (iii)). The limit doesn't touch grading, offsite improvement, or other postentitlement permits (clause (iv)), and within the two rounds the statute doesn't limit how much feedback a city gives (§65913.3(h)).
- Inspections. No request or requirement at inspection that deviates from the approved plans, unless the city makes written findings, based on substantial evidence in the record, that no reasonable person could read those plans as compliant or that the change is needed for a specific, adverse impact on public health or safety (§65913.3(d)(5)).
- Appeals. A final written determination within 30 business days for projects of 25 units or fewer, or 45 for 26 or more; after a denial or a missed deadline you can seek a writ of mandate (§65913.3(e)(2)–(3)).
- Who it covers. Housing development projects (§65913.3(k)(1)). The statute doesn't name individual trade permits, so for work on an existing home, ask the building department before counting on it.
How long a California building permit takes has the review clocks this limit sits inside.
EV chargers: SB 1283
From January 1, 2027, the streamlined approval cities must give EV charger permits also covers a charger with a canopy or on-site battery storage sized to support charging. An application that is deemed approved gets written notice within 30 days, and construction can start before the notice arrives. Cities update their checklists by December 31, 2027 (Gov. Code §65850.7(b), (g)(1)(C); §65850.71(g)).
SB 1283 (Chapter 347, Statutes of 2026) was approved by the Governor on September 20, 2026. It amends Gov. Code §65850.7, which requires the streamlined process, and §65850.71, which holds the deadlines. The §65850.71 amendments "become operative on January 1, 2027" (§65850.71(i)(2)).
- What the approval covers. A city must approve an EV charging station administratively, through a building permit or similar nondiscretionary permit, "including, but not limited to, an electric vehicle charging station with a canopy or onsite energy storage systems sized to support charging" (§65850.7(b)). The expedited process also covers supporting infrastructure: paving, a concrete pad, a utility trench, a canopy, or on-site storage (§65850.7(g)(1)(A)).
- Canopy size. A clearance height of 17 feet or less, a fascia width of 4 feet or less, and a coverage area of 5,000 square feet or less (§65850.7(j)(2)).
- The deadlines stay, counted by EVSE. An application is deemed complete after 5 business days for 1 to 25 EVSEs at a single site, or 10 for more than 25, if the building official has neither deemed it complete nor issued a written correction notice detailing all deficiencies and the additional information the review needs (§65850.71(b)). It is deemed approved 20 or 40 business days after that, "with no notice or public hearing required," if the official hasn't approved it, denied it, found on substantial evidence that the station could have a specific adverse impact on public health or safety, or required a use permit, and no appeal has been made (§65850.71(c)). An EVSE is "a device with one or more charging ports and connectors for charging electric vehicles" (§65850.7(j)(5)); today's text counts "electric vehicle charging stations" instead.
- Written notice. Within 30 days of a deemed approval, the city gives written notice of the date and of the permits and authorizations granted. You may start construction before that letter arrives (§65850.71(g)).
- Where the city has no updated checklist. The application must contain everything the statute lists, including location, number of EVSE units, contacts, voltages, output power, make and model, service and circuit ratings, load figures, site grade, canopy and storage details where present, and documentation of compliance with §65850.7(b) and (f) (§65850.71(f)(1)(A)–(P)). The Governor's Office of Business and Economic Development is to adopt a standard form for it (§65850.71(f)(3)).
- What the city keeps. It can require the plans and documents needed to verify health and safety compliance and can inspect the work as built, with plan check run through the expedited process (§65850.7(i)). A finding of a specific, adverse impact on public health or safety can still send the application to a use permit (§65850.7(b)).
The EV charger guide covers the permit itself: the load calculation, the documents, and the inspections.
ADU impact fees: SB 1117
From January 1, 2027, for up to two ADUs on a lot, impact fees on an ADU larger than 750 square feet may be charged only on the area above 750 square feet, still in proportion to the primary home. An ADU of 750 square feet or less, or a junior ADU of 500 or less, already pays none (Gov. Code §66311.5(c)(1)).
SB 1117 (Chapter 809, Statutes of 2026) was approved by the Governor on September 29, 2026 and amends Gov. Code §66311.5.
- Up to two ADUs on a lot. Fees on an ADU over 750 square feet of interior livable space are charged "proportionately in relation to the square footage of the primary dwelling unit, and only on the area in excess of 750 square feet" (§66311.5(c)(1)(B)).
- More than two ADUs on a lot. The fee stays proportional to the primary home, on the whole unit (§66311.5(c)(1)(C)).
- What an impact fee is. A fee under Gov. Code §66000(b) or §66477. It does not include a connection fee or capacity charge (§66311.5(c)(2)).
Each city's ADU guide, linked from the city guides, covers the permit and the state review clock.
Dates in order
Five dates cover these changes, January 1, 2027 to July 1, 2028. A section with no date of its own starts when its act takes effect, January 1, 2027 (Cal. Const., art. IV, §8(c)(1)).
- January 1, 2027. AB 1621's plan check limit and appeal deadlines (Gov. Code §65913.3), SB 1283's EV charger amendments (§65850.7; §65850.71(i)(2)), and SB 1117's ADU fee rule (§66311.5(c)(1)). Under SB 222: the heat pump permit fee cap (§51297.57), posted requirements and fees and electronic signatures (§51297.56), the limits on local standards and site plans (§51297.54), and the HOA rules (Civ. Code §4737). AB 1738 takes effect too, with its duties due in 2028 (Health and Safety Code §17970.9(b)).
- July 1, 2027. Asynchronous inspections for heat pump water heaters and heat pump HVAC in existing homes (Gov. Code §51297.52(a)).
- December 31, 2027. Cities finish amending their EV charger ordinances and checklists (Gov. Code §65850.7(g)(1)(C)).
- January 1, 2028. Remote inspections on request in cities over 50,000 and in counties, unless exempt (Health and Safety Code §17970.9(b)(1), (b)(3)). It is also the date written into SB 222's one-permit section (Gov. Code §51297.53(a)).
- July 1, 2028. Remote inspections in cities of 50,000 or fewer that aren't exempt (Health and Safety Code §17970.9(b)(2), (j)(2)), and real-time online permits for heat pump swapouts (Gov. Code §51297.55(a)).
Which duties skip small cities and counties
Four duties exempt a city with fewer than 5,000 people and a county with fewer than 150,000, along with every city in that county: the heat pump fee cap, the posting duty, real-time online permits, and remote inspections. Asynchronous inspections and the other three laws have no population exemption.
| Duty | Section | Cities under 5,000; counties under 150,000 and their cities |
|---|---|---|
| Heat pump permit fee cap | Gov. Code §51297.57(a)(2) | Exempt |
| Posted heat pump requirements and fees, electronic signatures | Gov. Code §51297.56(c) | Exempt |
| Real-time online heat pump permits | Gov. Code §51297.55(d) | Exempt |
| Remote inspections on request | Health and Safety Code §17970.9(b)(1) | Exempt |
| Asynchronous heat pump inspections | Gov. Code §51297.52 | Not exempt |
| One permit per heat pump installation, limits on local standards | Gov. Code §§51297.53–51297.54 | Not exempt |
| Plan check limit, EV charger approvals, ADU impact fees | Gov. Code §§65913.3, 65850.7, 65850.71, 66311.5 | No population exemption |
The statutes don't say which population count applies. If a city is near a threshold, ask its building department.
On the job
- Heat pump bids. Once a city posts its heat pump permit fee, compare it with the cap. In a city that isn't exempt, a fee above $150 or $200 should trace to an adopted resolution or ordinance (§51297.57(b)).
- Load calculations. Keep the calculation in the job file. For heat pump HVAC, a real-time permit rests on your certification under penalty of perjury, and the city can ask for the calculation (§51297.55(a)(3)).
- Remote inspections. Get the homeowner's written consent before you request one. If the city requires the inspection to be remote, you tell the homeowner about that requirement instead (§17970.9(a)(1), (a)(3)).
- Housing plan check. Count the review rounds. After the second, the city can deny, and further submittals are yours to request (§65913.3(c)).
- EV chargers. If the city hasn't updated its checklist, build the application from the statute's full list (§65850.71(f)(1)).
Where getPermit fits
getPermit doesn't file permits or handle inspections. It's a pre-launch AI permit coordinator for California contractors, aimed at the step before filing: what a city will expect, with a human coordinator reviewing every assessment. Today you can join the waitlist.
FAQs
What California permit laws take effect in 2027?
Five laws signed in September 2026 take effect January 1, 2027: SB 222 (heat pump permits, Gov. Code §51297.50 et seq.), AB 1738 (remote inspections, Health and Safety Code §17970.9), AB 1621 (plan check on housing, Gov. Code §65913.3), SB 1283 (EV charger permits, Gov. Code §§65850.7 and 65850.71), and SB 1117 (ADU impact fees, Gov. Code §66311.5). Several of the new duties start later, the last on July 1, 2028 (Gov. Code §51297.55; Health and Safety Code §17970.9(b)(2)).
Is there a cap on heat pump permit fees in California?
From January 1, 2027, yes. Under SB 222 a city or county may not charge a permit fee above its estimated reasonable cost, and not more than $150 for a residential heat pump water heater or $200 for a residential heat pump HVAC system in an existing home (Gov. Code §51297.57). A city can charge more only through an adopted resolution or ordinance with substantial evidence of its cost. Cities under 5,000 people, and counties under 150,000 with the cities in them, are exempt.
When do California cities have to offer remote inspections?
By January 1, 2028, or July 1, 2028 for cities of 50,000 or fewer, for heat pump water heaters, heat pump HVAC at the inspector's discretion, residential reroofs, PV up to 15 kW AC, energy storage, and smoke and CO detectors in one- and two-family homes (Health and Safety Code §17970.9, added by AB 1738). Cities under 5,000, and counties under 150,000 with the cities in them, are exempt. Separately, from July 1, 2027, every city and county must offer asynchronous inspections, or remote inspections in their place, for heat pump installations in existing homes (Gov. Code §51297.52, added by SB 222).
What is a heat pump swapout under SB 222?
An installation where the new heat pump water heater, or the new air handler and outdoor coil, goes in the same location as the equipment it replaces. A job that modifies, replaces, or installs more than 25 linear feet of ductwork, or that changes a package unit to a split system or the reverse, is not a swapout (Gov. Code §51297.51(d)). Swapouts need no site plan (§51297.54(a)(1)). By July 1, 2028, a swapout that needs no new electrical panel or structural work gets its permit online in real time, with a load calculation certification for HVAC, except in exempt small cities and counties (§51297.55).
Does SB 1283 change the EV charger permit deadlines?
The day counts stay the same, but from January 1, 2027 they are counted by EVSE (a charging device) instead of by charging station. An application is deemed complete after 5 business days, or 10 for more than 25 EVSEs at one site, if the building official has neither deemed it complete nor issued a written correction notice detailing all deficiencies and the additional information the review needs. It is deemed approved 20 or 40 business days later unless the official has approved it, denied it, found on substantial evidence that the station could have a specific adverse impact on public health or safety, or required a use permit, or an appeal has been made (Gov. Code §65850.71(b)–(c), (i)(2)). SB 1283 also extends the streamlined approval to chargers with a canopy or on-site battery storage, and requires written notice within 30 days of a deemed approval (§65850.7(b); §65850.71(g)).