Duct replacement permits in San Francisco, CA

General California guidance last updated November 14, 2026 · San Francisco data fully re-verified

Do you need a permit?

In California, replacing or extending ductwork requires a mechanical permit, and the Energy Code (Title 24, Part 6) treats it as an alteration: replacing a duct system entirely — or adding or replacing more than 25 feet of duct — generally triggers duct sealing with third-party HERS leakage testing. Ducts must meet the insulation R-value for the climate zone. A C-20 (HVAC) licensed contractor generally pulls it.

San Francisco accepts submittal through the Permit Services at DBI (online permits and tracking) and has adopted the SF Building Code (2025 edition, amending the 2025 California Building Code). Fee details and sources are below.

San Francisco permit data

Sourced from public City of San Francisco documents — every field carries the source URL and verification date.

Permit portal
Permit Services at DBI (online permits and tracking)

verified Aug 9, 2026 · source · Online filing for electrical, plumbing, mechanical, and Boiler-to-Operate permits (one-time contractor registration required); In-House Review building permits are filed via Electronic Plan Review (EPR). The PermitSF portal (https://sanfranciscoca.portal.opengov.com/) covers sign, awning, no-plans reroofing, and door/window/siding replacement permits. Permit tracking at https://dbiweb02.sfgov.org/dbi_building/

Adopted code edition

SF Building Code (2025 edition, amending the 2025 California Building Code)

verified Aug 9, 2026 · source · Ordinance 231-25 repealed the 2022 Building Code and enacted the 2025 SF Building Code — the 2025 California Building Code and 2025 California Residential Code as further amended by San Francisco — operative January 1, 2026 (ordinance text: https://sfbos.org/sites/default/files/o0231-25.pdf). Designed to be used in conjunction with the 2025 California Building and Residential Codes.

How duct replacement permits work in California

Ductwork replacement is permitted mechanical work across California, and the review is mostly an Energy Code review. Title 24, Part 6 treats duct work as an alteration: replace the system, or add or replace more than 25 feet of duct, and duct sealing with third-party HERS leakage verification generally follows — specified on the CF1R-ALT, with your CF2R and the rater's CF3R registered before final (Title 24, Part 1, §10-103; Reference Appendix RA2.8). The materials are checked too: insulation at the climate zone's required R-value (R-6 or R-8 in most cases), joints sealed with mastic or listed UL 181 tape — never cloth-backed duct tape — and flex duct supported so it isn't kinked or compressed. Because the HERS rater is independent, the schedule needs their test and registration between substantial completion and final inspection; CF1R, CF2R, CF3R and the HERS rater lays out that order. Fees, permit forms, and inspection scheduling are set per city — confirm with the local building department.

For deeper background that isn't San Francisco-specific, see the statewide duct replacement guide.

Pulling HVAC permits in San Francisco?

Get on the waitlist for this city.

Code basis

2025 California Building Standards Code (Title 24), which applies to permit applications filed on or after per the California Building Standards Commission. Sections checked against the published code; cities may add local amendments.

  • California Mechanical Code (Title 24, Part 4) §104.1 — Permits Required: a mechanical permit before installing, altering, repairing, replacing or remodeling a mechanical system; §104.2 (Exempt Work) covers only portable appliances and like-for-like component replacement that does not alter the appliance's approval.

    source

  • California Mechanical Code (Title 24, Part 4) §603.0 — Installation of Ducts: flexible air ducts (§603.4), support of ducts (§603.7) and joints and seams with listed closure systems (§603.9), the rule behind the no-cloth-tape correction.

    source

  • California Mechanical Code (Title 24, Part 4) §605.0 — Insulation of Ducts; §601.2.1 carries the California Energy Code's residential return-duct sizing requirements.

    source

  • California Energy Code (Title 24, Part 6) §150.2(b)1D — Altered duct systems: more than 25 feet of new or replacement duct triggers insulation per Table 150.2-D (R-6 in Climate Zones 3 and 5 through 7, R-8 elsewhere) and duct sealing confirmed by field verification and diagnostic testing, with 5 percent leakage allowed for an entirely new or complete replacement system.

    source

Typically needs a permit

Duct replacement needs a permit in nearly every California jurisdiction, San Francisco included.

Usually no permit

  • Maintenance sealing of accessible duct joints (verify locally)
  • Replacing registers and grilles
  • Repairing insulation on existing ducts

If a customer asks you to skip the permit, see what skipping the permit costs a California contractor.

Documents & plans generally required

Before you pay someone to assemble and file the package, see what a permit expediter costs in California.

Common reasons duct replacement applications get bounced

Common across California; this is not San Francisco rejection data.

Each correction round adds review time. For the review deadlines and two-review limit state law sets for housing permits (the limit starts January 1, 2027), see how long a California building permit takes.

The inspection sequence

A typical order — the number of stops and exact sequence vary by jurisdiction and scope.

  1. 1Rough inspection where ducts are concealed in framing before cover
  2. 2Final inspection with the system complete and the HERS duct-leakage results registered where required

For what inspectors check in each trade, what a failed inspection means, and the remote inspection rules that start in 2027 and 2028, see California building inspections for contractors.

Licensing — who can pull it

Duct replacement in California is generally C-20 (HVAC) licensed work; a B (General Building) contractor may pull within a larger remodel under CSLB rules. The HERS duct test is performed by an independent third-party rater, not the installing contractor.

For what each CSLB class may take on its own, when the owner pulls the permit instead, and what the law says about pulling a permit for someone else's job, see which California contractor license can pull which permit.

Other verified San Francisco notes

FAQs

Does a duct repair need a permit?

Small like-for-like repairs are often treated as maintenance, but replacement and extension are permitted mechanical work — and once more than 25 feet of duct is new or replaced, the Energy Code's sealing-and-testing requirements generally come with it. Describe the real scope; cities notice 'repairs' that replace half a system.

What leakage does the HERS test allow?

The allowed leakage is a percentage of system airflow set by the Energy Code, and it differs for new, entirely replaced, and altered duct systems. Seal every joint with mastic, have an independent HERS rater test the ducts, and register the results — an unregistered test doesn't close the permit.

What R-value do ducts need?

Title 24 sets duct insulation by climate zone — commonly R-6 or R-8 for ducts in unconditioned space, with R-8 required in many zones. The CF1R-ALT documents the value for the project's zone, and both the inspector and the HERS rater look at the duct label.

Do I need a separate permit if I'm also replacing the furnace or AC?

Usually one mechanical permit covers both scopes, but the energy paperwork compounds — the equipment changeout triggers its own measures and the duct replacement its own. The trap is pulling an equipment-only permit and 'discovering' the duct replacement at final.

Pulling HVAC permits in San Francisco?

Join the waitlist. We prioritize the cities and trades our early users work in.

San Francisco · HVAC, taken from this page